Airport Construction Project Update Week 1:
The Contractor installed erosion and traffic control and began working on the watermain extension this week.
Watermain installation will continue into early next week after which they will begin sanitary sewer installation.
They anticipate being completed with utility extensions next week and then begin construction of the pavement section for the Taxiway A3 and Taxilane Bravo extensions.
If you have any questions or comments about the construction project, please contact Silas at 612-987-0138 or silas.parmar@bolton-menk.com
-------------------------------
Construction of the Taxiway A3 and Taxilane Bravo extension projects will begin on Monday, July 15th and is scheduled to be completed on August 16th. The project will involve extending Taxiway A3 from parallel Taxiway A to Taxilane Bravo and extending Taxilane Bravo to the north of Taxiway A2. Sanitary and watermain utilities will be extending along with Taxilane Bravo for future private hangar connections.
During this time, access to existing Taxiway A3 between parallel Taxiway A and Runway 31 will be closed.
Weekly construction updates will be provided at the end of each week.
You can view the Project Layout here.
If you have any questions or comments, please contact Silas Paramar at 612-987-0138 or silas.parmar@bolton-menk.com